Phase I:
Toddler and Children’s House Village East
The expansion, renovation, and reconstruction of Chesapeake Village, formerly the Multi-purpose Building.
Start: January 2017
Completion: November 2017
Phase II:
Toddler and Children’s House Village West
Restoration and redevelopment of Potomac Village, formerly the Main Building.
Start: November 2018
Completion: June 2018
Recent Updates
August 2017 Capital Project Update
Our children are back on campus and classes are in full stride! The month of August brought many exciting updates, along with some hiccups. Our entire community has worked together to overcome these challenges with grace and strength. The Toddler and Children's House...
June 2017 Capital Project Update
In June, our building project hit full stride – we have seen walls literally pop up overnight! Although many of our families and staff are off for the summer, our construction continues on and it is great to see the amazing progress. The half of the Multipurpose...
May 2017 Capital Project Update
Though the ample spring rains have been trying at times, the project found a much more productive rhythm in May. After spending April in a battle of wills with the vein of Cockeysville Marble running through the site, rock breaking yielded to a considerable amount of...

Inspiring Workspaces
A well-designed, well-constructed, and well-preserved environment is critical to providing real life settings for our children to develop confidence and innovation; rising as responsible, compassionate, and empowered leaders, learners, and advocates.

Direct Access to Outdoor Learning
The entire learning environment – from the classroom materials to the social setting, to the landscape and architecture – must be supportive of the Montessori child’s personality, health, and well-being for self-directed learning to transpire.

Peer-Oriented Villages
Our newly constructed, renovated, and restored environments are created with students at the heart. Our villages each speak to the specific needs of the respective age group promoting connection, leadership, community support, and activism.
The school will contribute at least $600k to the project.

The school hopes to raise $500k with the Capital Campaign.
The school has received approval for a loan up to $3 million for Phase III.